Update on Scottish Power works with temporary lights at Tanners Lane/Lower Street junction in Haslemere

This morning, I spoke on site with the Scottish Power project coordinator and crew who are working in Haslemere and have set up the temporary lights by the Lower Street and Tanners Lane junction.

They tell me they have extended their road closure licence until the 24th April for the temporary traffic lights. 24th April is the worse case scenario end date for the lights.

Scottish Power will amend their signage to reflect a change in date to 24th April

I explained that the current signage states the work will finish on 5th March and that it would be helpful to set expectations by amending the details on the board. They have agreed to do this.

The project has taken longer than expected due to complications. These have included cables at one building that were 8m down and required deep excavation, some pipes that had pushed into drains and, the poor weather.

They tell me the lights will be recalibrated in the next few days as the company will move their works to the other side of Lower Street.

I have arranged a further meeting with the site manager for next week to discuss further.