Tag Archives: SSE

Update – Lower Street, Haslemere – SSE Works Mains Cable Replacement

I had a site meeting this morning with SSE management to discuss their works on Lower Street.

Lower Street will be opening on Monday morning, with traffic light controls as there is still work to carry out on one side of the carriageway as they have major hurdles to overcome- including extremely old multiple service pipes.

Traffic lights are expected for 2-4 weeks.

High Pavement works will then follow.

It’s disappointing that SCC Highways were not able to take the opportunity to resurface this stretch of road during the closure.

Lower Street Roadworks To Be Brought Forward In Haslemere

I thought it would be helpful to share this letter following my request that the planned major utilities (SSE Major cabling upgrade) works on Lower Street are brought forward. I have consulted with my fellow town councillors and the Haslemere Chamber of Trade and Commerce, and agreed that the works should start as soon as possible in the hope that the works are completed before businesses in town are able to fully reopen.

This is the text of the letter:

I believe you are aware of the SSE Major cabling upgrade works on Lower Street which will require a Road Closure. These works were originally planned to take place this Summer Holidays, however I’ve been informed that you’ve asked if these works could be brought forward whilst the shops are still closed.

I’ve spoken to SSE and they can bring these works forward and have provided me with a planned start date of the 01/06/2020 (provided that you’re happy with this). The duration of the works will be 6 weeks (with the end date being 18/07/2020), however this is the worst case scenario and SSE are confident that they can complete the works quicker than this.

If they do get the go ahead, the Advanced Warning Signs will be placed on Monday 18th May and Letter drops carried out also on this date which gives members of the public and local residents/businesses plenty of notice.

Lower Street will be closed from 1 June

The diversion route will be Tanners Lane, West Street, High Street which has been used before and works well. The parking bays outside the shops on West Street will have to be suspended.

Please could you advise if you would be happy with this?

Kind Regards,

Network Coordinator – Waverley

Streetworks Team

Network and Asset Management Group

Surrey Highways

Temporary Traffic Signals Along A286

I would like to inform you of some works due to start on April 7 2014. SSE will be undertaking works to renew High Voltage electricity cables utilising temporary traffic signals along the Grayswood Road between Highercombe Road and Lower Road.

The works are essential and are to replace electricity cables which (as I am sure you are aware), have recently failed resulting in many residents being left with generators providing their electricity supply. The works have an anticipated duration of approximately one month.

In order to minimise traffic congestion we have permitted the works to start early and utilise the Easter break when schools will be closed.

Whilst works along this road are never desirable removing generators and providing residents with a new robust electricity supply would seem paramount.