This morning, I spoke on site with the Scottish Power project coordinator and crew who are working in Haslemere and have set up the temporary lights by the Lower Street and Tanners Lane junction.
They tell me they have extended their road closure licence until the 24th April for the temporary traffic lights. 24th April is the worse case scenario end date for the lights.
Scottish Power will amend their signage to reflect a change in date to 24th April
I explained that the current signage states the work will finish on 5th March and that it would be helpful to set expectations by amending the details on the board. They have agreed to do this.
The project has taken longer than expected due to complications. These have included cables at one building that were 8m down and required deep excavation, some pipes that had pushed into drains and, the poor weather.
They tell me the lights will be recalibrated in the next few days as the company will move their works to the other side of Lower Street.
I have arranged a further meeting with the site manager for next week to discuss further.
Several residents brought to Surrey County Council’s attention the overflowing drain in Lower Street.
I have been out with the jetter at the Lower Street crossing, investigating the drainage problem. The drain has been jet washed and a camera probe sent down, revealing a blockage in the pipe under Lower Street. The team think it is probably a water utility pipe.
Next steps… SCC highways to obtain a street works permit to excavate the road in order to repair the problem.
Here is an email I have received re Lower Street road closure:
From:On Behalf Of Works Communication Team/EAI/SCC To: Nikki Barton <Nikki.Barton@surreycc.gov.uk> Subject: Lower Street, Haslemere – Resurfacing works (Road Closed)
Dear Cllr
Barton
I am writing to advise you that we will be closing the road on the
27 September and the 4 October whilst we carry out our surfacing works.
To facilitate this we will need to close the road from 9:30 until
16:00 on each Friday to enable us to park our lorry near to the site.
There will be no access for vehicles during this time.
Outside of the above closures, we will continue to use three way
lights until the end of the works.
I am sharing an update regarding works on Lower Street, Haslemere. The works within Lower Street itself are complete and the team have now moved into the garage area.
Prior to the works starting the
team carried out site investigations of both the pipe systems and ground
conditions. The ground condition survey had
shown mild asbestos levels that were not sufficient to cause concerns with
regard to safety. However, when the team started digging in the garage
forecourt today, they found much higher concentrations of asbestos. As a result of this works had to cease.
The team now need to get positive
confirmation it is asbestos, then assess the risks posed, and then proceed with
appropriate measures in place to safely continue their works – this process may
take some time. In the interim period the team will be working in other areas
to maintain progress of the overall job at hand.
Thank
you for getting in touch. Firstly I would like to provide some background on
the purpose of this work and the complications this scheme has presented.
The
works on Lower Street involve construction of new drainage and are primarily to
remove a flood risk to a property where the highways drains pass beneath it, by
rerouting our pipes. This involves digging a new pipe through private land in a
restricted area, between two houses and a garage parking area, through a
retaining wall, along a footpath and to a chamber.
There are a great deal of utility services underneath the road surface (please see below pictures and map) and ultimately it is these services which actually dictate what is possible. Due to the significant amount of underground services the team are using a vacuum excavator as this is a far safer way for our team to remove spoil than a conventional digger. Using this equipment mitigates any risk to their personal safety, which is of utmost importance to us.
We
have gatemen present at each end of Lower Street, their role is to remain at
either end of the road and ensure the public do not enter the live works site.
The area the team are working in is outside of a property called Tisa Cottage.
Whilst they may not be visible from either end of the road, I can assure you
that the team are on site, working extremely hard on a daily basis and are
making progress.
On
Monday I was advised that the team had got to a point where they have found the
unknown buried pipe and this has determined the level for the rest of the
works. Our engineer believes they have found a route through the services to
allow installation of the new pipework and the team on site are working towards
this. There are difficulties with some of the existing pipes which the new
pipes need to be connected to, as they are encased in brick. This may mean that
the team have to dig further to achieve the connections or do something a
little differently. The excavations are a bit larger than initially hoped for
but unfortunately this is unavoidable. Please see attached a copy of the
original plans for this scheme which should demonstrate what the team set out
to achieve.
Looking
at the original plans it is clear that this a particularly difficult site with
many utility services, this makes progress slow and the design has to be
adapted to suit what is unearthed. The team had previously investigated as
thoroughly as possible having camera surveyed the drain runs and used ground
probing radar to identify services and hence a probable route for the new
pipes, however it is only when the ground is actually excavated that the
realities of the situation are revealed.
The
equipment being used, the width of the road and the size of excavation required
mean that a road closure is necessary. Another reason, that may not be
immediately obvious, is that live traffic cannot run too close to the hole due
to the pressure that is transmitted to the sides of the excavation by vehicles.
We really don’t want to close roads unless we have to and do not make the
decision lightly. There are many variables we have to consider including the
site operations, the size of the road and the safety of both the travelling
public and our work force. For Lower Street this criteria meant a closure.
Please see attached site diaries from the 7 and 8 August which detail work progress with photographic evidence of work taking place. Please be advised these site diaries belong to one individual on site and their start time does not necessarily reflect the time that everyone was on site.
The
lead engineer on this project is satisfied with the progress on site.
Considering the difficulties the team have faced, they are working extremely
hard and going the extra mile where necessary to support the residents living
in the works area, whilst carrying out their work to a good standard. I hope
this help to reassure you and your residents that work is taking place and
progress being made.
In
view of the above, I will be updating our road works map pop-out with a PDF
document that explains the work and has pictures of our progress so far. I hope
that this will highlight to the public the challenges the team have faced on
this scheme and the extent of works being carried out. I’m hoping that
explaining what we are trying to achieve will justify the length of time we
need for this work and why it is essential that the road is closed whilst we
carry out the work.
I
would be very grateful if you could direct your residents to the information on
roadworks.org and if there are further queries please could they be sent to us
in the Works Communications Team.